Public Home > FIDELIS > Ambassador Way > Installation
       

Installation

week of Sunday 10/30 through Thursday 11/03/2011 - installation of two 35' Ambassador Way pylons and 4 sets of Burlington wall signs

 
Sunday
Oct 30, 2011

New footing locations by D.M. and pics of building

    • 10 files
  •  
    Monday
    Oct 31, 2011

    Footings drilled and base pipe set for two new 35' pylon structures

    • 15 files
  •  
    Tuesday
    Nov 1, 2011

    Installation: phase 1 of pylon sign - and - front Burlington letters started

    • 17 files
  •  
    Wednesday
    Nov 2, 2011

    Completion of two 35' pylon signs and installation of front 3 sets Burlington signs

    • 11 files
  •  
    Thursday
    Nov 3, 2011

    Burlington side set of 7' channel letters installed and wired

    • 7 files